Skip to main content

HPN Elevator Renovation and Upgrade Project Update

CURRENT STATUS: Otis Elevator Installation Crew is on-site and work has begun on two elevators.

Otis Elevator has spent the past 5 months completing all of the preliminary work needed before actual start of the installation. This included finalization of all design elements and systems architecture, as well as the specification and ordering of long-lead parts and components.

On Friday, October 2nd, the formal Project Kick-off meeting was held at HPN. Attendees included the HPN Board, HPN Property Manager Tom Downey, Project and Crew managers from Otis, and the account manager from our consulting firm Michael Blades (MBA). All aspects of the project implementation were reviewed and discussed, and the Project Implementation timeline was updated.

KEY PROJECT MILESTONES – MBA will provide Project Management support until final acceptance

  • Mobilization October 5-9 Storage container placed on-site @ HPN; most materials received & stored
  • Car #1 October 12th - car taken out of service; Car returned to service January 29, 2016
  • Car #2 October 12th - car taken out of service; Car returned to service January 29, 2016
  • Car #3 January 8th - car taken out of service; Car returned to service April 7, 2016
  • Project Completion Punch-List - April 7th - April 13, 2016

We sincerely regret that only one (1) elevator will be available during the next three months, including over the Holiday period between late November and January 1st. This schedule, though inconvenient at times, should allow us to accelerate completion of the entire project.